The main driver for this project is to deliver efficiency gains to ERI, RGS and Colleges. This will be done by removing the need to double key information by harmonising reporting requirements, removing duplication of effort, and better capturing the information required to support the grant administration process. This development will reduce complexity and make the supporting spreadsheets, databases and processes obsolete N.B. This project is phase 2 of the Infinite system development.  Phase 1 being developed under project RES017

 

N.B. this project was started before the move to the new projects website, so documentation is only shown from 6th August 2012.   Documentation prior to this can be found on the old site at http://www.projects.ed.ac.uk/areas/research/general/RES032/index.shtml

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2013 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
Research Administration: Infinite
Code
RES032
Programme
Z. Research (RES) (closed August 2017)
Project Manager
Adam Wadee
Project Sponsor
Nigel Paul
Current Stage
Close
Status
Closed
Start Date
04-Mar-2010
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2013
Overall Priority
Higher
Category
Discretionary

Project Dashboard

Change dashboard

Nothing to report.