March 2019

Report Date
March 2019

Achievements this month

  • jQuery review document reviewed with team

Issues

Next Steps

  • Write closure report.
  • Close project.

 

Milestones

Deliver Final deployment sign-off 18-Jan-2019
Close Closure 25-Jan-2019
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
BLUE
RAG Commentary
Amber as Final cost over budget- no further change now code all deployed. Additional effort around live deployment/support . Additional budget will come from the ring-fenced SSP resources. Completed the review the final release with lessons learned and recommendations made to the team & Senior Supplier. Time is also amber due to delay to close project
Change Status
Has formal escalation taken place?
Yes
Escalated to
Senior Supplier
Change Commentary
Marked as closed as approved by WIS 12/4
Activity
Approved budget
80.0 days
Activity this month
0.0 days
Activity this year
120.0 days
Activity to date
181.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Jquery Library Upgrade
Code
SAC069
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Gregory Carter
Project Sponsor
Defeng Ma
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Apr-2018
Planning Date
30-Apr-2018
Delivery Date
11-Jan-2019
Close Date
11-Apr-2019
Programme Priority
3
Overall Priority
Normal
Category
Compliance

Documentation