- Report Date
- June 2018
Achievements this month
- First batch of changes made and tested.
- Release slots booked.
Issues
- Original budget insufficient to deliver all of the scope. Budget increase approved and project re-planned accordingly.
Next Steps
- Continue working through the established backlog and releasing to a fortnightly schedule, as per other SSP projects.
- Approved budget
- 50.0 days
- Activity this month
- 19.0 days
- Activity this year
- 28.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 40.0 days
- Estimate to complete future years
- 34.0 days