Report for July 2018

Report Date
July 2018

Achievements this month

  • Continuing to work through backlog - satisfied that current rate of progress will lead to completion within the budget.

Issues

  • None.

Next Steps

  • Continue as is.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
105.0 days
Activity this month
25.0 days
Activity this year
55.0 days
Activity to date
61.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
45.0 days

Project Info

Project
Jquery Library Upgrade
Code
SAC069
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Gregory Carter
Project Sponsor
Defeng Ma
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Apr-2018
Planning Date
30-Apr-2018
Delivery Date
11-Jan-2019
Close Date
11-Apr-2019
Programme Priority
3
Overall Priority
Normal
Category
Compliance