Organisation
Project Plan
Please see Project Plan
Work/Task Breakdown
Phase of work |
Objective |
Task(s) |
Who is involved? |
| Initiation | O1&O2 |
|
Project Team |
| Planning | O1&O2 |
|
Project Manager Project Team
|
| Analysis | O1 |
|
Business Analysts SSP Dev Team DevTech |
| O2 |
|
||
| Build | O1 |
|
SSP Dev Team |
| O2 |
|
||
| Build Peer Review | O1&O2 |
|
SSP Dev Team Project Manager SSP |
| Test | O1 |
|
SSP Dev Team |
| O2 |
|
SSP Dev Team | |
| Documentation & Comms | O1&O2 |
|
BA team SSP Project Manager |
| Acceptance | O1&O2 |
|
Student Systems Operations |
| Implementation | O1 |
|
SSP Dev Team BA team Project Manager |
| O2 |
|
||
| Delivery | O1&O2 |
|
Production Technology Lead |
| Post-LIVE checks & sign off deployments | O1&O2 |
|
Student Systems Operations Production Technology Lead |
| Closure | O1&O2 |
|
Project Manager Project Team |
Resources, Skills and Costs
The initial budget for this project was medium size (120 days) and only accounted for IS APPs and not USG resource. This was a placeholder figure pending estimations that were to be completed throughout the planning stage of the project and the development of its project brief.
We have now reviewed and re-estimated the required work. The analysis completed related to the data migration work highlighted extra strands of required work; such as the downstream integrations.
The project is larger and over a longer duration, although there is a dependency in agreeing the new data retention policy as part of Objective 2.
Total Project Budget is now estimated at 327 days and includes the following:
- 204 IS APPs (including SSP Development), split as follows:
- 23/24 - 100.2
- 24/25 - 84.9
- 123 SSP Business Analysts/Tester, split as follows:
- 23/24 - 64.6
- 24/25 - 58
- Resource from the Reporting Team and Student Systems Operations are not included in this budget.
- Objective 2 estimation for development work is 30 days, based on previous work deleting unsuccessful applicant data which took 10 days to run. Based on the initial anlysis of large tables, we are expecting to run 3 X deletions.
Project Governance
This project will follow the standard project governance in Project Services.
Any changes to major milestones (Initiation, Planning, Delivery, Closure) will be approved by the Project Sponsor, Project Team and Apps Review.
Major milestones achievements and changes will be submitted to Apps Review for approval/noting as necessary.
Project Stakeholders
| Name | Business Area | Role | Communication Plan |
|---|---|---|---|
| Anastasia Mezecka (PROJECT TEAM) | SSP | Business Analyst |
Weekly catch-up meetings |
| Andy Crossland (PROJECT TEAM) | SSP | Senior Business Analyst |
Weekly catch-up meetings |
| Craig Warrack (PROJECT TEAM) | Student Systems Operations | Business Lead |
Weekly catch-up meetings |
| Defeng Ma (PROJECT TEAM) | SSP | Developer |
Weekly catch-up meetings |
| Douglas Adamson (PROJECT TEAM) | Apps Production Management | Apps Lead |
Weekly catch-up meetings |
| Ewan Wilson (PROJECT TEAM) | SSP | Developer |
Weekly catch-up meetings |
| Franck Bergeret | SSP | Programme Manager |
Weekly catch-up meetings |
| Gillian Simmons | SRA Director's Office | SRA Admissions |
Ad-hoc |
| Jack Ross (PROJECT TEAM) | Project Services | Project Manager | |
| Jamie Morton | Student Systems Operations | BI Reporting Manager |
Ad-hoc |
| Jim Galbraith | Governance and Strategic Planning | Governance and Strategic Planning |
Ad-hoc |
| Julie Gifford | Student Analytics, Insights and Modelling | HESA Return |
Ad-hoc |
| Luke Manley (PROJECT TEAM) | SSP | Tester |
Weekly catch-up meetings |
| Mark Lang (PROJECT TEAM) | Apps Development Services | Technology Lead |
Weekly catch-up meetings |
| Peter Donoghue (PROJECT TEAM) | SSP | Developer |
Weekly catch-up meetings |
| Stefan Kaempf | Applications Directorate | Senior Supplier |
Ad-hoc |
