Impact

Priority and Funding

  • Priority 3 (normal)
  • Core - College Ring Fenced 60 days

Impact and Dependencies

The Project Marking Tool is a CSCE only product and is developed, hosted and managed from within the CSCE. Therefore, there is no expected organisational impact.

There are no known external project dependencies  

Project Risks

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner Date of Last Review
1 Product Scalability GREEN GREEN Open Retain Keith Brunton 22-Oct-2018
2 Assumption: "The tool will be made available to other schools through existing School of Physics and Astronomy infrastructure" is incorrect GREEN GREEN Open Reduce Keith Brunton 22-Oct-2018
3 CSCE Developer Resource Commitments GREEN GREEN Open Retain Keith Brunton 22-Oct-2018

Project Info

Project
College Project Marking Tool
Code
SCE014
Programme
SCE Portfolio Projects (OTHSCE)
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Victoria Dishon
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
15-Jun-2018
Planning Date
09-Nov-2018
Delivery Date
20-Sep-2019
Close Date
14-Feb-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary