Approval
Approval Record
|
Check List Item |
Quality Criteria |
Complete Y/N |
Reviewed By |
|
Category and Billing Arrangements |
|
Y |
Susan Duff Jamie Thin |
|
Scope, Objectives and Deliverables |
|
Y |
Susan Duff Jamie Thin Scott Rosie and wider project team |
|
Milestones |
|
Y |
Jamie Thin Scott Rosie Steph Ruthven and wider project team |
|
Costs |
|
Y |
This is an annual recurring compliance project - at 150d per year - until the current tecnology stack is replaced 5 year costs = 5 x150d = 750d IS Apps effort |
|
Procurement Approach |
|
Y - n/a |
not applicable - annual changes to existing system within 10-year contract |
|
Benefits |
|
n/a |
This project is compliance - if this project is not delivered - the University of Edinburgh could no longer deliver a shared academic Timetabling service across the whole university beyond Jan 2017 |
|
Project and Service Impacts |
|
Y |
Susan Duff Jamie Thin Suran Perera |
|
Risk |
|
Y |
Susan Duff Jamie Thin |
|
Roles and Stakeholders |
|
Y |
Susan Duff Jamie Thin |
|
Resource Estimate |
|
Y |
Susan Duff Jamie Thin |
|
Project Plan |
|
Y |
Susan Duff Jamie Thin |
Approval Record
|
TOR Raised By |
Susan Duff / Jamie Thin |
|
Date Raised |
22-Nov 2016 |
|
Date TOR Reviewed |
23-Nov-2016 |
|
Date TOR Approved |
29-Nov 2016 |