Completion Report

Project Summary:

The stated objective for this project was:

  • To deliver a report that includes an estimate and high level plan to deliver the upgraded infrastructure needed for the new version of ThankQ.

This report has been prepared and delivered after consultation and estimation with the stakeholders.

Analysis of Resource Usage:

Staff Usage Estimate: 5 days

Staff Usage Actual: 4.5 days

Staff Usage Variance: -10%

Other Resource Estimate: 0 days

Other Resource Actual: 0 days

Other Resource Variance: 0%

Explanation for variance:

The only variance to report is that the consultation with colleagues in IS Apps took slightly less time than anticipated.

Key Learning Points:

There were no lessons learned under this project.

Outstanding issues:

There are no reported issues outstanding.

Project Info

Project
D&A - ThankQ Analysis
Code
USG001
Programme
USG Portfolio Projects (OTHUSG)
Project Manager
David Watters
Project Sponsor
Pete Morrison
Current Stage
Close
Status
Closed
Start Date
23-Jun-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2015
Programme Priority
1
Overall Priority
Normal
Category
Discretionary