Organisation

Organisation

Work/Task Breakdown 

Project Phase/Task Name

Planning

  • Produce Project Brief
  • Identify stakeholders
  • Produce estimates
  • Produce plan
  • Planning Review

Analysis and Design

  • Communications and requirements gathering
  • Develop options documentation based on workshops and engagement with stakeholders
  • Report findings and produce initial definition options for IID based on requirements 
  • Breakdown preferred technical solutions and refine the solution definition
  • Define service offering and agree with stakeholders.

Delivery and Acceptance

  •    Delivery of documented recommended solutions based on ranked requirements

Closure

  •    Produce Closure Report
  •    Closure Sign-Off
  •    Closure

 

Resources, Skills and Costs 

Link to spreadsheet for estimates.

Download the pdf extract for the plan.

Staff from Development Technology and Technology Management will be utilised, with involvement from other sections as required. The agreed solution will require resources from both Applications and ITI.

Project Governance

The project sponsor is Dave Berry, the Programme Manager is Chris Copner and the project manager is Don MacIver. 

This project will follow the standard project governance in Project Services.

Any changes to major milestones (Initiation, Planning, Delivery, Closure) will be approved by the Project Sponsor, Project Team and WIS.

Major milestones achievements and changes will be submitted to WIS for approval/noting as necessary.

 

Project Stakeholders

Name                                          

Business area                                                                                             

Role

Adam Wheavil

IS Applications Production Management

Production Management Representative (Project Team Member)

Adam Wadee

Project Services

Resource Management

Alex Carter

IS Applications - Head of Service Management

Service Owner (Member of Programme Board)

Alison Armstrong

ISG

Portfolio Manager (Member of Programme Board)

Ana Heyn

IS Applications Production Management

Production Management Representative

Bill Lee

Development Services

Development Services Representative

Brandi Headon

Student Services Operations Manager

Student Services Service Manager

Jason Dove

IS Applications Project Services

BA (Project Team Member)

Chris McKay 

IS Applications Production Management                                        

Service Manager for IDM (Business Lead and Project Team Member)

Emma Robertson-Werner

EUSA (Marketing)

Student Comms Oversight

Dave Berry

IS Applications

Enterprise Architect & Programme Owner and Project Sponsor; (Member of Programme Board)

Defeng Ma

IS Applications Development Services

Student Services Partnership

Gavin McLachlan

IS CIO

IS CIO

Graeme Wood

ITI (Section Head of Enterprise Services)

ITI Representative (Member of Programme Board)

Hugh Brown

Production Management

Production Management Lead (Project Team Member)

Garry Scobie

 Rep for CISO and Alistair Fenemore

InfoSec (Project Team Member)

Iain Fiddes

IS Applications Head of Development Services

Senior Supplier(Member of Programme Board)

James Jarvis

Colleges and Schools

C&S Representative for A Majothi (Member of Programme Board)

Jerrard Doran

Student Services Head of Business Process Enhancement  

Student Services Representative for L Dawson

John Bannaghan

Finance

Finance Rep

Kenny MacDonald

IS ITI enterprise Services

ITI Senior Computing Officer (ITI Lead)

Mark Ritchie

ISG

Senior Stakeholder

Michael Sun

IS Applications Development Services

Lead Developer (Project Team Member)

Neil Bruce

Operational Services

Assurance for communications and transition to BAU

Megan Brown/ Natalie Hay

EUSA

Student representation (Member of Programme Board)

Stephen Smith

IS Applications (Service Management)

O365 Service Manager (Project Team Member)

Susan Cooke

Enterprise Data Services Team

 Resource Management
Dawn Dodd and Catherine Hetherington Service Management  Resource Management

Susan McLaren

HR Systems and Business

HR Service Manager 

 

 

 

 

Project Info

Project
Define Integrated Identities Requirements
Code
DTI039
Programme
Digital Transformation - Integrated Identities (DTIP09)
Management Office
ISG PMO
Project Manager
Hilary Shand
Project Sponsor
Dave Berry
Current Stage
Close
Status
Closed
Start Date
01-Feb-2018
Planning Date
25-Aug-2018
Delivery Date
07-Sep-2018
Close Date
28-Sep-2018
Overall Priority
Normal
Category
Discretionary