Organisation

Work/Task Breakdown

Task Name Duration Start Finish Predecessors Resource Names % Complete
Project Initiation 4 days Mon 02/09/19 Fri 06/09/19     100%
   Initial Technical Meeting 1 day Mon 02/09/19 Mon 02/09/19   PM+Tech 100%
   Initial Finance Meeting 1 day Thu 05/09/19 Thu 05/09/19   PM+Fin 100%
   Initiation Complete 0 days Fri 06/09/19 Fri 06/09/19   PM 100%
Project Planning 15 days Mon 09/09/19 Fri 27/09/19     29%
   Launch Meeting with 3rd Party 1 day Tue 10/09/19 Tue 10/09/19   PM+Tech 100%
   Project Brief Written 5 days Mon 09/09/19 Fri 13/09/19   PM 100%
   Procurement of Servers 10 days Mon 16/09/19 Fri 27/09/19   Tech 0%
   Project Brief Review/Revision/Sign-off 4 days Mon 16/09/19 Thu 19/09/19 7 PM+Tech+Fin 0%
   WIS Submission 1 day Fri 20/09/19 Fri 20/09/19 9 PM 0%
   Planning Complete 0 days Fri 20/09/19 Fri 20/09/19 10 PM 0%
Project Execute (Build) 11 days Mon 30/09/19 Mon 14/10/19     0%
   Implementation Plan 1 day Mon 30/09/19 Mon 30/09/19 8 Tech 0%
   Build of Servers 4 days Tue 01/10/19 Fri 04/10/19 13 Tech 0%
   Back-Up Database 1 day Mon 07/10/19 Mon 07/10/19 14   0%
   Install Software on Servers 4 days Tue 08/10/19 Fri 11/10/19 15 Tech 0%
   Update Documentation 1 day Tue 01/10/19 Tue 01/10/19 13 Tech 0%
   Install Client Software on Windows 10 PC       1 day Mon 14/10/19 Mon 14/10/19 16 Fin 0%
   Build Complete 0 days Mon 14/10/19 Mon 14/10/19 18 Tech 0%
Project Execute (Test) 2 days Tue 15/10/19 Wed 16/10/19     0%
   UAT 2 days Tue 15/10/19 Wed 16/10/19 19 Fin 0%
   UAT Complete 0 days Wed 16/10/19       Wed 16/10/19       21 Tech 0%
Project Delivery 10 days Mon 07/10/19 Fri 18/10/19     0%
   IS Alert/Go-CAB 5 days Mon 07/10/19 Fri 11/10/19   PM 0%
   Deployment Checklist 1 day Tue 15/10/19 Tue 15/10/19 19 Tech 0%
   Deployment 1 day Thu 17/10/19 Thu 17/10/19 22 Tech+Fin 0%
   Business Checkout 1 day Fri 18/10/19 Fri 18/10/19 26 Fin 0%
   Delivery Complete 0 days Fri 18/10/19 Fri 18/10/19 26 PM 0%
Project Closure 11 days       Fri 25/10/19 Fri 08/11/19 28   0%
   DSOR 1 day Fri 25/10/19 Fri 25/10/19 28 PM+Tech+Fin 0%
   Create Project Closure Report 4 days Fri 01/11/19 Wed 06/11/19 30 PM 0%
   Review Project Closure Report 2 days Thu 07/11/19 Fri 08/11/19 31 PM+Tech+Fin 0%
   Project Closure 0 days Fri 08/11/19 Fri 08/11/19 32 PM 0%

 

Resources, Skills and Costs

Resource and skills are as documented under Project Stakeholders and by role. 

A project budget of 20 days has been secured to fund the project.

 

Project Governance

The project will follow the standard governance and quality control as used by Project Services and IS Applications. This covers WIS and monthly reporting

The project will be monitored against the work/task breakdown with wider reporting by exception.

The project team will meet on a fortnightly basis to:

  • Review progress in relation to the project plan and budget
  • Review any emerging issues
  • Review the project risk register
  • Confirm activities for the following period.

Meetings will be face-to-face with minutes taken.

Project Stakeholders

Name Business Area Role
Alister Webb (Project Team Member) Development Services Database and Systems Administrator
Andrew Dickinson (Project Team Member) Finance Assistant Accountant
Ashleigh Kelly (Project Team Member) Finance Management Accountant
Craig Henderson (Project Team Member) Finance Project Sponsor
Douglas Stewart (Project Team Member) Finance Business Lead
Emma Mcnab (Project Team Member) Project Services Portfolio Manager
Fernando Munoz Murga (Project Team Member)       Production Management       Database and Systems Administrator
John McFarlane (Project Team member) IT Infrastructure Senior Systems Administrator
Kevin Hone (Project Team Member) Project Services Project Manager (Project Team Member)

 

Project Estimations

Role Days
Project Manager 06
Systems Administrator 03
System & Database Administrator    06
Programme Manager 01
Production Management 02
Contingency 02
Total 20

 

 

 

Project Info

Project
Corporate Planner Upgrade
Code
FIN133
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Craig Henderson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
20-Sep-2019
Delivery Date
17-Oct-2019
Close Date
08-Nov-2019
Overall Priority
Normal
Category
Compliance