Deliver

The overarching objective of this project is to establish and evaluate an initial pilot Subtitle for Media service led by student subtitling editors, and make recommendations for future sustainability and resourcing.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2019 GREEN 34.0 days 28.0 days 52.0

Student-community projects to improve the designs of Hunter and Nicolson Square and follow-up from those.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2019 GREEN 0.0 days 0.0 days 0.0

Internship researching sustainability in the Festival Fringe at University of Edinburgh venues.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2019 GREEN 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2019 GREEN 0.0 days 0.0 days 0.0

This annual project will upgrade SITS software to the latest supported version 9.7.0 (was 9.5.0).

Benefits:

  • Student Record system remains within the standard support contract with SITS supplier Tribal 
  • Access to new functionality in new version

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2019 GREEN 200.0 days 141.0 days 61.0

An analysis piece carried out by an external consultancy to provide a recommendations report regarding the Encryption at Rest of student data held across central ISG.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2019 GREEN 33.0 days 32.0 days 2.2

This project will deliver an upgraded Serengeti Database Upgrade.

Serengeti is used to retain electronic copies documents where the purchase orders are generated and printed in eFinancials and the invoice is sent to Corporate Finance by the supplier.

Serengeti is also used by Estates Finance Control

2018/19

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2019 GREEN 61.0 days 27.0 days 38.0

Project Findings Reports

The following Reports are the findings from the Project:

1.  ITIRS_Proof of Concept - IBM Protocol Nodes Report:

IBM Protocol Nodes Report

 

2.  ITIRS_Proof of Concept - IBM Cloud Object Storage Report:

Project Findings Reports

The following Reports are the findings from the Project:

1.  Service Integration Review Report:

itirs_scheduler_review-1.2.1.doc

 

2.  The  Univa Grid Engine Assessment Report: