Project Status Reports

Title Report Date Time Cost Scope Overall Change
July 2019 July 2019 GREEN GREEN GREEN GREEN
June 2019 June 2019 GREEN GREEN GREEN GREEN
May 2019 May 2019 GREEN GREEN GREEN GREEN
April 2019 April 2019 GREEN GREEN GREEN GREEN
March 2019 report March 2019 GREEN GREEN GREEN GREEN
February report February 2019 AMBER GREEN GREEN AMBER
January 2019 January 2019 AMBER AMBER GREEN AMBER Moderate
December 2018 December 2018 AMBER AMBER AMBER AMBER Moderate
November 2018 November 2018 RED GREEN RED RED Significant
October 2018 October 2018 RED AMBER AMBER RED
Report for September 2018 September 2018 RED AMBER AMBER RED Moderate
Report for August 2017 August 2018 GREEN GREEN AMBER AMBER No Change
Report for July 2017 July 2018 GREEN GREEN AMBER AMBER
Report for June 2017 June 2018 AMBER GREEN AMBER AMBER
Report for May 2017 May 2018 RED AMBER AMBER RED
Report for April 2017 April 2018 AMBER AMBER AMBER AMBER
Report for March 2018 March 2018 GREEN GREEN GREEN GREEN
Report for February 2018 February 2018 GREEN RED GREEN RED
Report for January 2018 January 2018 AMBER RED GREEN RED
Report for December 2017 December 2017 GREEN GREEN GREEN GREEN
Report November 2017 November 2017 GREEN GREEN GREEN GREEN
Report for October 2017 October 2017 RED GREEN RED RED
September 2017 September 2017 RED GREEN RED RED
August 2017 August 2017 GREEN GREEN GREEN GREEN

Project Info

Project
Assessment and Progression 3
Code
SAC063
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Franck Bergeret
Project Sponsor
Susan Rhind
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
21-Aug-2017
Planning Date
26-Jan-2018
Delivery Date
31-Jul-2018
Close Date
30-Aug-2019
Overall Priority
Normal
Category
Discretionary