- Overview
This programme manages the development of the University's Digital Research services and infrastructure to support the University's strategic goal of Excellence in Research.
This is the section's set of projects delivering benefits to users of technology and services through transformation, growth and ongoing maintenance projects. As a whole, the projects are related by their shared resource, overall budget and broad alignment to strategic objectives so is more a sub-portfolio with the overall ITI portfolio than a formal programme of projects related to a common outcome in benefits or capability.
- Contacts
Programme Owner and Section Manager : David Fergusson Programme Manager : Maurice Franceschi
Code | RAG | RAG Date | Manager | Status | Stage | |
---|---|---|---|---|---|---|
RSS057 | Research Infrastructure Rolling Replacement Cycle | BLUE | July 2019 | Andy Todd | Closed | Close |
RSS055 | Scheduler Upgrade | BLUE | June 2020 | Peter Sanderson | Closed | Close |
RSS054 | Cloud Infrastructure Development | BLUE | July 2019 | Andy Todd | Closed | Close |
RSS053 | Accounting and Monitoring into Operation | BLUE | August 2020 | Peter Sanderson | Closed | Close |
RSS052 | Platforms for Digital Humanities | BLUE | July 2020 | Peter Sanderson | Closed | Close |
RSS051 | Improving Access Interfaces for Compute and Data | BLUE | August 2020 | Peter Sanderson | Closed | Close |
RSS050 | DRS Website Development | BLUE | December 2019 | Maurice Franceschi | Closed | Close |
RSS048 | Storage Manager Operational Transition | BLUE | June 2023 | Mike Wallis | Closed | Close |
RSS044 | Data Vault III - Continuing Development | BLUE | February 2020 | Lawrence Stevenson | Closed | Close |
RSS038 | Group auditing and monitoring | BLUE | August 2018 | Peter Sanderson | Closed | Close |
RSS035 | Collaborative development of Storage Manager | BLUE | August 2018 | Peter Sanderson | Closed | Close |
RSS031 | DRS Outreach Phase II | BLUE | January 2019 | Maurice Franceschi | Closed | Close |
RSS029 | Backup Infrastructure Upgrade | BLUE | July 2019 | Andy Todd | Closed | Close |
RSS022 | Data Vault | BLUE | March 2019 | Lawrence Stevenson | Closed | Close |