Close
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2024 | GREEN | 0.0 days | 0.0 days | 0.0 |
Project Summary
Servers have been migrated and load balancers replaced.
There was virtually no interruption to services during this processes (one instance of Euclid being unavailable for a day).
|
Description of the Objective |
Success Criteria |
|
|
Description of the Deliverables needed to achieve the objective |
Project Summary
The project delivered a new Service that offers large scale virtual synchronous teaching : over 200 students can access their own virtual device in the same lecture theatre and at home, for example.
Benefits
Benefits have been delivered but limited to a very few courses.
Analysis of Resource Usage:
Explanation for variance:
Project Summary
Summarise the project : did it achieve its deliverables and objectives (see project brief and any subsequent changes), scope changes, overall review.
Benefits
Benefits already enabled by the Project
Future Benefits post-project.
Did the project deliver any innovation amongst these benefits?
Dis the project contribute to any of the Change Management Themes?
Project Manager must add benefits to the ITI Benefits Log (and communicate to the IS Change Management team if appropriate).
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
August 2024 | AMBER | 0.0 days | 0.0 days | 0.0 |
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
July 2024 | GREEN | 0.0 days | 0.0 days | 0.0 |
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
October 2024 | GREEN | 0.0 days | 0.0 days | 0.0 |
To provide project management for the Sharepoint team and Production Management team for the 24/25 Making Transitions Personal Review.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2024 | BLUE | 0.0 days | 0.0 days | 0.0 |