Close

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2024 GREEN 0.0 days 0.0 days 0.0

Project Summary

Servers have been migrated and load balancers replaced. 

There was virtually no interruption to services during this processes (one instance of Euclid being unavailable for a day).

 

 

 

Description of the Objective

Success Criteria

 

 

Description of the Deliverables needed to achieve the objective

Project Summary

 

The project delivered a new Service that offers large scale virtual synchronous teaching : over 200 students can access their own virtual device in the same lecture theatre and at home, for example. 

 

 

Benefits

Benefits have been delivered but limited to a very few courses.

 

 

 

Analysis of Resource Usage:

 

Explanation for variance:

 

 

 

Project Summary

Summarise the project : did it achieve its deliverables and objectives (see project brief and any subsequent changes), scope changes, overall review.

 

 

Benefits

Benefits already enabled by the Project

Future Benefits post-project.

Did the project deliver any innovation amongst these benefits?

Dis the project contribute to any of the Change Management Themes?

Project Manager must add benefits to the ITI Benefits Log (and communicate  to the IS Change Management team if appropriate).

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2024 AMBER 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2024 GREEN 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2024 GREEN 0.0 days 0.0 days 0.0

 

To provide project management for the Sharepoint team and Production Management team for the 24/25 Making Transitions Personal Review.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2024 BLUE 0.0 days 0.0 days 0.0