This annual project will upgrade SITS software to the latest supported version 10.5 (was 10.3, completed in Apr 22).
Benefits:
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
May 2023 | GREEN | 210.0 days | 157.2 days | 5.2 |
Two legacy Biomedical teaching applications that require upgrading as they are on an old version on Python
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
October 2022 | BLUE | 0.0 days | 0.0 days | 0.0 |
- Read more about The Archive of Tomorrow: Health Information and Misinformation in the UK Web Archive
The Archive of Tomorrow project, funded by the Wellcome Trust, aims to explore and preserve online information and misinformation about health and the Covid-19 pandemic. The project will preserve 10,000 websites relating to health, both official and unofficial. They form a 'Talking about Health' collection within the UK Web Archive, giving researchers and members of the public access to a wide representation of diverse online sources.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
June 2023 | BLUE | 0.0 days | 0.0 days | 0.0 |
This project will deliver the replacement of the fibre channel (FC) infrastructure supporting the DataStore service at the Mary Somerville (formerly JCMB) Data Centre. The scope covers installation, testing and replacement of fibre channel cabling, trunking, switches, and other components in the network. In addition, the scope includes the removal and disposal of legacy fibre channel equipment once the new infrastructure is in operation.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
February 2023 | BLUE | 48.0 days | 50.0 days | 0.0 |
This project is financed and focused on CMVM.
The overall aims are :
- to review the current data sources and management techniques,
- to provide an overview of how best to leverage the data the College is currently generating
- to improve the outputs and outcomes of the marketing team through better use of data insights,
- to ensure there is ongoing analytics support services in place to evolve the framework in order to adapt new techniques, tools. and industry best practice.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
February 2023 | BLUE | 0.0 days | 0.0 days | 0.0 |
To upgrade Scientia products to new Technology One Scientia supported versions. Since Scientia was acquired by Technology One - retirement dates have now been set for all previous versions of the Scientia products , as the products get migrated to Tech One supported products.
Current software versions are out of formal support from 1-Oct 2022. Technology One won't make any code changes to fix problems customers experience with these products after 1-Oct 2022. However Tech One support team will still support data errors that don't require changes to software code
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
June 2023 | GREEN | 200.0 days | 128.8 days | 0.3 |
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
February 2023 | GREEN | 0.0 days | 0.0 days | 0.0 |
St Cecilia’s meeting spaces – REPRICE
St Cecilia’s Hall QSC – mic upgrades
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
June 2023 | GREEN | 0.0 days | 0.0 days | 0.0 |
Small enhancements to the data warehouse, including the HR datamart. This project will manage small enhancements not covered by larger projects and will enable a responsive service. It is needed now because the BI Team has dedicated resource and the P&M managed projects, which have previously taken all the teams effort, are closing.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
September 2023 | GREEN | 500.0 days | 570.4 days | 54.9 |
The golden copy space database is held on Archibus, the accuracy and quality of this information at building and room level is relatively high. However, current data held centrally does not capture all the information now required by Estates and the wider University.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
July 2022 | AMBER | 50.0 days | 3.0 days | 47.0 |