Close
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| July 2025 | GREEN | 0.0 days | 0.0 days | 0.0 |
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| July 2025 | GREEN | 0.0 days | 0.0 days | 0.0 |
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| July 2025 | GREEN | 0.0 days | 0.0 days | 0.0 |
Project Summary
Following internal audit recommendations, it has been observed that the Mac user community has permanent admin privileges on their workstations/Laptops. In order to bring these devices in line with university security policy the decision has been made to implement the 3rd party software ‘Privileges’.
The project scope was
Ensure the upgrade of student computer lab, teaching and meeting room PC's across the College estate.
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| August 2025 | BLUE | 0.0 days | 0.0 days | 0.0 |
* Each space will get a desk from the decanted RAAC Teaching Spaces
ECA E.26
Joseph Black T40, & G.69
Grant 304B
North East Studio Building J.03 & J.05
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| July 2025 | GREEN | 0.0 days | 0.0 days | 0.0 |
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| March 2025 | GREEN | 0.0 days | 0.0 days | 0.0 |
There are regular requests for programme level feeds for Learn to allow Schools to provide Learn spaces for programmes with all students from a specific programme enrolled.
Some schools manually manage spaces with programme enrolments currently. This allows the schools to provide students on programmes with programme level information within a course site in Learn. Programme level assessment has been discussed at various Curriculum Transformation meetings and this work will help to support that those outcomes.
Current project status
| Report Date | RAG | Budget | Effort Completed | Effort to complete |
|---|---|---|---|---|
| July 2025 | GREEN | 0.0 days | 0.0 days | 0.0 |