Weekly update w/c 10/09/12

  • Project Brief ready for review by stakeholders
  • Timeline replanned around Dev Team's recruitment activities
  • Stores workshop re-planned for 24th September
  • New risk identified regarding lack of end-user input into requirements gathering (User Stories) - see Risk Log for further information

Project Info

Project
eStores Rollout
Code
FIN084
Programme
Finance (FIN)
Project Manager
Dawn Holmes
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
13-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Dec-2012
Programme Priority
2
Overall Priority
Normal