Monthly Progress Report DRAFT

Report Date
February 2016

Achievements:

  • Live rollout out in February 16.
  • HSM Personal Ids set up for 11 SAS Finance approvers and users
  • Deployment sign off review (DSOR) has been completed and Finance will now use C-series for all runs
  • Rollout in Live underway, already 10 file type have already been progressed, 2 underway and 5 to be run (when they apply)
  • HSM password actively underway and being used, with Finance SAS to progress (8/11 HSM users active so far)

Issues:

  • None

Next Steps:

  • Deployment sign off review (DSOR) will follow once Finance SAS have agreed Live is correct and that all file types have been run using C-series
  • Remaining HSM personal ids to be active and to be in use
  • 5-7 file types still to be actively used by confirming successful use of C-series

Project has been smoothly progressing with virtually all work being completed by SAS Finance

Milestones

DateMilestone
05-May-2016Closure
05-May-2016Decommission Albacs
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
80.5 days
Activity this month
4.4 days
Activity this year
54.5 days
Activity to date
73.0 days
Estimate to complete current year
7.2 days
Estimate to complete future years
0.0 days

Project Info

Project
ALBACS Replacement
Code
FIN106
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2016
Programme Priority
2
Overall Priority
Normal
Category
Compliance