Completion Report

Project Summary:

Scope

Replace end-of-life payment utility (ALBACS) with the new supported product (C-Series)

Objectives

To replace ALBACS with C-series both of which are supplied by Bottomline Technology

The project objective has been achieved  -  Albacs has been replaced by C-Series

Deliverables

The replacement of ALBACS with C-series is to deliver:

 DeliverablesPriorityCompleted
1Mechanism for approving and authorising outgoing BACS payments (like-for-like) - complete  must complete  
2Mechanism for authorising and sending Direct Debit instructions and collections (like-for-like)must complete
3New infrastructure - Test and Live serversmust complete
4Installation (only) of code for outgoing International payments (new)must complete
5Documented process for Disaster Recovery and Business Continuitymust complete (documented in Section 5 of the TAD)
6Decommission ALBACS after completion of successful payment runsmust complete (Albacs switched off)
7HSM (Hardware Security Module) was purchased and has been delivered during this projectmust complete

All the above project deliverables have been met.

Benefits

  • The C-series application is supported by Bottomline (and will be able to continue having outgoing payments supported)
  • International payments will now be possible, at a later date, under a future Finance project. International payments are currently paid manually via Santander and reconciled manually.
    • Having the international module installed will allow for a future review on how these payments are dealt with.
  • There is now a test site for C-Series, which means that future upgrades and patching can be fully tested before deploying to the Live service.
    • Now that there is a test site for C-Series any future changes to the Bank used by UoE can be tested before deploying to the Live service.
  • There was no current Disaster Recovery and Business Continuity processes documented. This project has provided this documentation, so that DR procedures can be formally set in place in future.

Success Criteria

 Success CriteriaAchieved
1Outgoing BACS payments are issued via C-Seriesyes
2Direct Debit instructions and collections are requested via C-Seriesyes
3Servers were purchased and installed on Test and Liveyes
4International Payments module has been installed onto Test and Live applications - installedyes (installed)
4.1

The intention is for Finance to be able to use International Payments (in future Finance projects) and to do this, required the module installed onto Test and Live applications - this has been done

Bottomline know what is agreed with the bank and how Finance make submissions to the bank (as there are multiple methods).

This is all that this project required - there was no intention to run International Payments in this project

yes (completed)
5Disaster Recovery and Business Continuity processes are documented and stored within IS/Finance - documentedyes (documented)

 

Analysis of Resource Usage:

Staff Usage Estimate: 60 days

Staff Usage Actual: 78 days

Staff Usage Variance: 30%

Other Resource Estimate: 0 days

Other Resource Actual: 0 days

Other Resource Variance: 0%

Explanation for variance:

Hardware Security Module - HSM and other delays

HSM (Hardware Security Module) work was added to the project and the project budget was increased to 80.5 days.

Delays to progressing the project during new student year (CAB) set up - see

  • The project Issue Log is available of the project website
  • For more information relating to scope changes (can be found in issues 8 and 10)
  • The introduction of HSM (Hardware Security Module) required restarting all servers (Issue 12)
  • Closure delayed to allow 3 months  running in LIVE before the decommissioning of Albacs (Issue 10)

The fact of installing HSM (Hardware Security Module) required all servers to be restarted before HSM (Hardware Security Module) could be activated involved a large service request to ensure it was planned at the correct time, which had an impact on the project's progress

There was a 4 month delay before the Vlan and HSM (Hardware Security Module) set up could be managed, more history relating to this can be found below:

  • Unidesk Call (reference I59820-0346) and its history in the journal of Networks and HSM set up (Issue 13)

Further to all this

  • Business were successfully responsible for verifying the Live testing (that is ensuring that all the current DD had run using C-series successfully
  • User id's were required for accessing the HSM (Hardware Security Module) user ids and 11 user ids were set up with a small number of them with admin authority to approve the work. Systems Accountants were responsible for ensuring that the 11 user ids were set up (working along with the supplier) to ensure personal ids were completed from a security point of view. This was looked after by the System Accountants

 

Key Learning Points:

Where different stakeholders require to be involved, ensure knowledge of what is required from all of the stakeholders early on, is established. eg - bank, ITI networks, production management, System Accountants (Finance) and Bottomline

 

Outstanding issues:

There are no outstanding issues related to this project.

Project Info

Project
ALBACS Replacement
Code
FIN106
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2016
Programme Priority
2
Overall Priority
Normal
Category
Compliance