Monthly Progress Report

Report Date
April 2016

Achievements:

  • No progress this month
  • Delay to Decommissioning Albacs due to higher priority requests for Dev Tech

Issues

  • None

Next Steps:

  • Decommission Albacs
  • Complete Albcas Closure

Milestones

13-May-2016Decommission Albacs
19-May-2016Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
81.0 days
Activity this month
1.0 day
Activity this year
56.0 days
Activity to date
75.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ALBACS Replacement
Code
FIN106
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2016
Programme Priority
2
Overall Priority
Normal
Category
Compliance