Monthly Progress Report

Report Date
July 2015

Achievements

  • Brief approved
  • Business Analysis drafted 29-Jul
  • Draft Systems Analysis coimplete
  • Systems Design review meeeting 3-Aug

Issues:

  • None

Next Steps:

  • Analysis complete
  • TAD complete
  • Systems Design complete
  • Order VM Servers
  • Set up VM Servers

Milestones:

Milestone DateMilestone Stage
07-Aug-2015Business Analysis
14-Aug-2015Systems Design
28-Aug-2015Installation Build
18-Sep-2015Integration
09-Oct-2015Acceptance
23-Oct-2015Deployment
30-Oct-2015Closure
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
9.6 days
Activity this year
18.6 days
Activity to date
18.6 days
Estimate to complete current year
0.0 days
Estimate to complete future years
45.4 days

Project Info

Project
ALBACS Replacement
Code
FIN106
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2016
Programme Priority
2
Overall Priority
Normal
Category
Compliance