Monthly Progress Report

Report Date
September 2015

Achievements

  • Programme meeting agreed that Albacs must remain for 3 months after C-Series is implemented to Live
  • Plan, milestones and estimates amended
  • All information Bottomline have requested has been provided

Issues:

  • Now that Special Cab period has completed, still no date from Networks as to when their work will be completed.
  • Dev Tech Manager following that up with Networks
  • This impacts the project and agreeind dates with Bottomline as they require 2 weeks notice before on site to begin work

Next Steps:

  • Networks to be available
  • Set up VM Servers
  • Provide any further information as required to Bottomline about Servers and Networks
  • Agree plan with Bottomline
  • Arrange Bottomline site visits
  • Bottomline initial visit to set up HSM

Milestones DRAFT dependent on Networks :

16-Oct-2015Installation Build
23-Oct-2015Integration
06-Nov-2015Acceptance
20-Nov-2015Deployment
04-Dec-2015Deployment Sign Off Review (DSOR)
08-Mar-2016Closure
08-Mar-2016Decommission Albacs
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
Change Status
Activity
Approved budget
80.5 days
Activity this month
5.0 days
Activity this year
22.1 days
Activity to date
40.7 days
Estimate to complete current year
40.8 days
Estimate to complete future years
0.0 days

Project Info

Project
ALBACS Replacement
Code
FIN106
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2016
Programme Priority
2
Overall Priority
Normal
Category
Compliance