Progress Report
- Report Date
- November 2015
Achievements:
- Bottomline were on site 5 Nov to set up the Hardware Security Module's (HSM's) although they were not connected at that point
- All ITI VM Servers were restarted on 24 -Nov to allow for the Hardware Security Module (HSM) to be connected in December
- Following that the VM Servers were set up with HSM
- Bottomline's 3 day visit took place on 1-3 Dec to set up TEST.
- Test was checked out and verified using C-series.
- Finance successfully completed initial Testing and Training.
- Agreed date with Bottomline regarding Live deployment set up
- Agreed Finance will actively use Live C-Series in January
Issues:
- None
Next Steps:
- Complete Acceptance Testing
- Agreed Live set up date as 21-Dec with Bottomline
- System will not become actively Live until January
- Live rollout out in January 16.
Test installation complete. Acceptance testing now underway.
Milestones
| Date | Milestone |
| 11-Dec-2015 | Acceptance |
| 17-Dec-2015 | Deployment |
| 29-Jan-2016 | Deployment Sign Off Review (DSOR) |
| 05-May-2016 | Closure |
| 05-May-2016 | Decommission Albacs |
- Approved budget
- 80.6 days
- Activity this month
- 10.6 days
- Activity this year
- 35.8 days
- Activity to date
- 54.4 days
- Estimate to complete current year
- 28.0 days
- Estimate to complete future years
- 0.0 days