Progress Report

Report Date
November 2015

Achievements:

  • Bottomline were on site 5 Nov to set up the Hardware Security Module's (HSM's) although they were not connected at that point
  • All ITI VM Servers were restarted on 24 -Nov to allow for the Hardware Security Module (HSM) to be connected in December
  • Following that the VM Servers were set up with HSM
  • Bottomline's 3 day visit  took place on 1-3 Dec to set up TEST. 
  • Test was checked out and verified using C-series. 
  • Finance successfully completed initial Testing and Training.
  • Agreed date with Bottomline regarding Live deployment set up
  • Agreed Finance will actively use Live C-Series in January

Issues:

  • None

Next Steps:

  • Complete Acceptance Testing
  • Agreed Live set up date as 21-Dec with Bottomline 
  • System will not become actively Live until January
  • Live rollout out in January 16.

Test installation complete. Acceptance testing now underway.

Milestones

DateMilestone
11-Dec-2015Acceptance
17-Dec-2015Deployment
29-Jan-2016Deployment Sign Off Review (DSOR)
05-May-2016Closure
05-May-2016Decommission Albacs
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
80.6 days
Activity this month
10.6 days
Activity this year
35.8 days
Activity to date
54.4 days
Estimate to complete current year
28.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ALBACS Replacement
Code
FIN106
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2016
Programme Priority
2
Overall Priority
Normal
Category
Compliance