Monthly Progress Meeting

Report Date
January 2016

Achievements:

  • Further testing took place in January
  • Acceptance Testing signed off
  • Deployed successfully in December
  • Requested Bottomline support to set up HSM Users accounts
  • Agreed rollout will take place in February

Issues:

  • None

Next Steps:

  • Finance will actively use C-series in  Live with old password while waiting for HSM Bottomline work
  • Deployment sign off review (DSOR) will follow once Finance agreed Live is correct then all the runs will follow with C-series
  • Agreed Finance will actively use Live C-Series as soon as accounts set up by Bottomline
  • Live rollout out in February 16.
  • Agree when project will be suspended and for how long

Milestones

DateMilestone
29-Jan-2016Deployment Sign Off Review (DSOR)
05-May-2016Closure
05-May-2016Decommission Albacs
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
80.6 days
Activity this month
7.8 days
Activity this year
50.0 days
Activity to date
68.6 days
Estimate to complete current year
11.3 days
Estimate to complete future years
0.0 days

Project Info

Project
ALBACS Replacement
Code
FIN106
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2016
Programme Priority
2
Overall Priority
Normal
Category
Compliance