Deployment

Deployment Strategy

Deployment date is Tuesday 22n August. There will be a period of downtime required as Dev Tech deploys the various scripts to update stored procedures and deploy the new eTime application code. Rollback procedures are in the implementation plan.

Dependencies

No dependencies identified with any other support or project work going on around Go Live date.

Communication

Finance to communicate to eTime users that the application will be unavailable during deployment. Any users in the application may lose unsaved work during deployment.

Project Team to notify the business when the deployment has completed.

Deployment Checklists

Application checklist

 

Component

Success Criteria

Project Stage Required (Agile)

OK (Y/N) Reviewed by (date) Outstanding Actions (Who)

Implementation Plan

Feedback from previous test implementations completed and successful full implementation undertaken for UAT

DSOR (Release 1-n)

Y

John Chan

17/08/2017

 

Implementation Risk Assessment

A risk assessment has been undertaken for the Implementation Plan and selected deployment dates. (e.g. roll back)

ASOR (Release 1-n)

Y

John Chan

17/08/2017

 

TAD/Operational Document

Documentation complete

Action: The Document must be copied to the Wiki

No changes to either documentation as part of this project.

 

Y

John Chan

03/07/2017

 

System Design Specification (SDS)

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

ASOR (Final Release  / Handover)

Y

John Chan

17/08/2017

 

System Description Document

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

ASOR (Final Release  / Handover)

Y

John Chan

17/08/2017

 

Scalability/Load Testing

Adequate load testing has taken place. The results have been recorded and analysed to ensure that the application will cope with the anticipated load.

No load testing to be done as part of this project as the number of users expected to be the same. Prior projects have done load testing.

ASOR (Final Release  / Handover)

N/A

John Chan

03/07/2017

 

Performance

The application has been tested against stated performance criteria. Performance has been assured by user and support staff testing.

ASOR (Final Release  / Handover)

Y

John Chan

 

 

Source Code

 

Source control must be checked out till go-live and checked-in after go live

Source code has been secured with SVN or other source control tool.

Action: ensure Production Branch created

Where code is provided by a third party (e.g. supplier) it has been established who is responsible to maintain source code

 

DSOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Configuration Management Database

The relevant details regarding new or changed infrastructure components have been added to the CMDB in unidesk

No change to the infrastructure as part of this project.

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Change Control(s)

A Change & Release record  has been created in unidesk for the LIVE implementation request.

 Action: record unidesk number

 Special CAB:C1708-045, C1708-058,C1708-134 (05/09/17)

 

ASOR / (Release 1-n)

Y

John Chan

03/07/2017

 

Test Log Review

A review of the test log (JIRA) has taken place to ensure all required actions have been completed.   If this is not the case, then confirmation on criticality of outstanding issues and action plan for resolution is required.

https://www.jira.is.ed.ac.uk/issues/?jql=project%20%3D%20FIN116

To be reviewed before acceptance sign off.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Production Management Handover

Handover to Applications Management and Technology Management is completed or arranged and the teams are in position to support the application post deployment.

Action: record handover dates

Handover between John Chan and Thalia on 17th August.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Support Accounts

Read access accounts or update current read access accounts have been set up for support staff(requires business owner approval)

No changes.

ASOR (Final Release  / Handover)

N/A

John Chan

03/07/2017

 

Password Management (Password Manager Pro)

Password Manager Pro has been updated with all relevant account details including external supplier  accounts

ASOR (Release 1-n)

N/A

John Chan

03/07/2017

 

Environment comparison

Database comparison between TEST and LIVE (might be required before and after go-live)

Minor database changes. Apps Man will check manually between TEST and LIVE as post deployment task.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Client requirements

Does the application have specific client requirements, such as JVM/JRE versions, JInitiator etc

If so have these requirements been raised with Desktop services

Wiki pages to be updated:

[1] https://www.wiki.ed.ac.uk/display/insite/Corporate+applications+with+client+based+requirements

[2] https://www.wiki.ed.ac.uk/display/insite/Client+side+requirements+for+corporate+applications

ASOR (Release 1-n)

N

John Chan

03/07/2017

 

Technologies

Is there any new software or technologies involved? (Y/N)

If yes state any additional actions taken to ensure adequate handover to the production support team

No new technologies involved.

ASOR (Release 1-n)

N

John Chan

03/07/2017

 

Access outside University

By default all web based applications are accessible outside University without use of VPN etc Wiki list

If not accessible from outside University this needs to be approved by Production Management.

No changes.

ASOR (Release 1-n)

N/A

John Chan

03/07/2017

 

Vendor Access Required

Does vendor require db/app access (Y/N)

If yes, ensure access details are in TAD

IS application.

ASOR (Final Release  / Handover)

N/A

John Chan

03/07/2017

 

Certificates

All changes to certificates or new certificates for this service have to be added to the certificate master list. The certificate master list is being managed by Applications Management This includes TEST and LIVE certificates and records type of certificate and expiry dates.

ASOR (Final Release  / Handover)

N/A

John Chan

03/07/2017

 

Deployment Date(s)

Agreed date has been confirmed that allows adequate time for completion of Acceptance Sign Off Review.

Check top of this document for deployment dates.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Deployment Resources

IS and business area resources required for deployment, including those needed for post implementation checking and sign off have been secured.

PM to resource and secure.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Deployment Ownership

Responsibilities for managing the go-live, including: comms with service owner and end users, ensuring go live timescales are met, managing issues arising and managing comms between all teams involved in go live.

PM to

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Service Announcement(s)

A Service announcement has been raised with the agreed deployment date on the alert system:

 

http://reports.is.ed.ac.uk/alerts/

 

Service announcements should be raised by Project Manager 10 days before go live, but no later than 4 days.

 

http://reports.is.ed.ac.uk/alerts/index.cfm?fuseaction=view_alert&alert_id=6985

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Reporting and Analytics

New BI Universes or substantial changes to Universes/report offerings need to be documented in the Information Portal managed by GaSP.

https://www.wiki.ed.ac.uk/display/IP/Information+Portal+Home

No changes to BI eTime universe.

 

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Infrastructure checklist

 

Component

Success Criteria

Project Stage Required (Agile)

OK (Y/N) Reviewed by (date) Outstanding Actions (Who)

Technical Architecture/Operational Document(TAD)

Documentation complete and accurately reflects the environment subjected to UAT.

No changes.

 

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Security

All security requirements, e.g. SSL encryption, IP based restrictions firewall requirements have been specified, tested and implemented in LIVE

No changes.

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

User Accounts

    Y

John Chan

03/07/2017

 

Patching

Ensure that all applications have an agreed patching schedule and this schedule is agreed with service owners. Different technologies have different patching strategies:

Oracle, Windows, Linux

No changes.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Start/Stop scripts

Are Server Start-up/Shutdown scripts in place?

Including start-up procedure documented, enabled and tested.

No changes.

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Ports

Port allocation file been updated:

 

https://www.wiki.ed.ac.uk/display/insite/Port+Allocation+on+Unix+Servers

No changes

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Backup and Recovery

All backups as noted in the TAD need to be confirmed operational.

 

A test recovery of user data needs to be done to validate the integrity of the recovery mechanism and process.

No changes.

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

DR Copy

DR copy to SECONDARY DB configured and tested (unless existing database which is already setup).

Existing DB.

ASOR/Release1

Y

John Chan

03/07/2017

 

Logs

For all logs the following is in place:

  • Logs are rotated and old logs are archived or deleted to ensure server space is not reached

  • In production only minimal levels of logging is switched on (debug may be adequate on DEV, but not on Production)

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

 Support checklist

 

Component

Success Criteria

 Project Stage Required (Agile)

OK (Y/N) Reviewed by (date) Outdstanding Actions (Who)

Support Agreement (including any charging arrangements)

A support agreement OLA is in place for any new applications – including any hosting or support charges. Where external suppliers are involved an SLA should be in place as well.

 

Action: SLA  moved to wiki:

 

https://www.wiki.ed.ac.uk/display/insite/SLA+repository+-+Applications+Management

No changes.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Time Recording Code

A Time Recording code for the application, if required, has been confirmed and set up (in ASTA)

Action: Does application require a separate entry for business area in ASTA

No changes.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Disaster Recovery and Business Continuity

Appropriate DR/BC provision is in place and has been fully tested. Application DR/BC details have been transferred to the DR Portfolio and DR level (1, 2 or 3) has been agreed

No changes.

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Test Environment

An adequate TEST environment has been established for the application which may be used by support to test future changes prior to releasing these in the LIVE environment.

No changes.

ASOR (Release 1-n)

Y

John Chan

03/07/2017

 

Hardware and Software Licensing

All required licensing is in place including maintenance/support arrangements with external suppliers.

No changes.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Browser Compatibility

Browser compatibility has been tested and compatibility information updated

See

http://www.ed.ac.uk/schools-departments/information-services/services/computing/application-development/application-support/supported-web-browsers/browser-application

 for details

No changes.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Portal Compatibility

Portal compatibility, where required, has been confirmed the Portals Service Owner.

No changes.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Help Desk

The new application is recognised with the UniDesk (A business contact queue is defined where initial calls are raised with)

No changes.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

User Guide Documentation

Appropriate documentation has been produced for users of the new application.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Training Material

Training material, if required, has been produced and is of an appropriate standard.

Finance to do.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Demonstration or Walkthrough

Demonstration or walkthrough of the new application has taken place for other stakeholder.

Finance to do.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

Web Sites and Other Document Sources

External and internal web sites have been reviewed to ensure that all application references are present, correct and up to date.

Finance to do.

ASOR (Final Release  / Handover)

Y

John Chan

03/07/2017

 

 

 

Project Info

Project
eTime 16/17
Code
FIN116
Programme
Finance (FIN)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Elizabeth Welch
Current Stage
Close
Status
Closed
Start Date
08-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Sep-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance