Project journal
Title | Description | Author | Post date |
---|---|---|---|
Third Business Stakeholder meeting notes available |
The BOXI Upgrade project has had it's third meeting with the business stakeholders, at this meeting there was discussion on the new licences and software, the migration of personal reports and a general update on the project progress. Meeting notes and presentation are available for anyone interested in the Business Objects upgrade. https://www.projects.ed.ac.uk/project/its092/page-5 |
Craig Middlemass | 09-Jul-2013 |
Weekly Project Team Meeting - 25 June 2013 and Sponsor Meeting Notes |
Work completed last week |
Craig Middlemass | 28-Jun-2013 |
Weekly Project Meeting - 4 June 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 04-Jun-2013 |
Weekly Project Meeting - 21 May 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 21-May-2013 |
Weekly Project Meeting - 14 May 2013 |
Work completed last week |
Craig Middlemass | 14-May-2013 |
ITS092 - Weekly Team Meeting 7 May 2013 - Draft |
Work completed last week
Issues Encountered |
Craig Middlemass | 07-May-2013 |
Senior Supplier / Project Manager Meeting 14th May 2013 |
1. Licence Discussion David Smyth and Simon Marsden are working on the licence dispute with SAP and this has a target resolution date of nth June 2013. The outcome of which will be complete resolution, breakdown impacting the upgrade and potential constrained continued use of the licences. 2 new risks will be created to cover these outcomes: |
Craig Middlemass | 14-May-2013 |
Weekly Update Meeting - 30 April 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 30-Apr-2013 |
ITS092 - Second Business Stakeholder Meeting |
The BOXI Upgrade project has had it's second meeting with the business stakeholders, at this meeting a demonstration of the new R4 Dev Environment was given along with a discussion on the training, communications and governance for the project. Meeting notes and presentation are available for anyone interested in the Business Objects upgrade. https://www.projects.ed.ac.uk/project/its092/page-5 |
Craig Middlemass | 06-May-2013 |
Senior Supplier / Project Manager Meeting 29th April 2013 |
1. Stakeholder Management Director of Apps very posiive on current direction for project but felt it important that various BI/MI related initiatives are joined up so that everyone understands what's going on and works together to maximise benefit. Current projects/initiatives include: |
Mark Ritchie | 29-Apr-2013 |
ITS092 - Monthly Sponsor Meeting April - Draft |
Discussion Points |
Craig Middlemass | 23-Apr-2013 |
Weekly Team Meeting - 18 April 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 23-Apr-2013 |
Weekly Team Meeting - 9 April 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 10-Apr-2013 |
Weekly Team Meeting - 2 April 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 02-Apr-2013 |
ITS092 - First Business Stakeholder Meeting |
The BOXI Upgrade project has completed its initial meeting with the business stakeholders, the meeting was well recieved. Meeting notes and presentation are available for anyone interested in the Business Objects upgrade. https://www.projects.ed.ac.uk/project/its092/page-5 |
Craig Middlemass | 01-Apr-2013 |
Weekly Team Meeting - 26 March 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 26-Mar-2013 |
Weekly Team Meeting 19 March 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 19-Mar-2013 |
Weekly Team Meeting - 12 March 2013 |
Work completed last week |
Craig Middlemass | 12-Mar-2013 |
Weekly Team Meeting - 26 Feb 2013 |
Work completed last week |
Craig Middlemass | 26-Feb-2013 |
Weekly Team Meeting - 19 Feb 2013 |
Work completed last week
Issues Encountered |
Craig Middlemass | 19-Feb-2013 |