Impact

 Priority and Funding

  • Priority has been set as 2 (HIgh)
  • Funding is from core budget of the FInance Programme
  • Current estimated budget allocated from annual planning is 450 days (214 days in 13/14 and 236 days in 14/15). This estimate will be validated during the Foundations stage when more is known about the requirements.

Impact and Dependencies

The project will require changes to the following systems: -

  • eAuthorisations
  • WebFIrst
  • MyEd
  • Business Objects

The project will interact with, and may be impacted by changes to, the following systems: -

  • eFInancials
  • EASE

The project may also interact with, and may be impacted by changes to, the following systems: -

  • Serengeti
  • FPM

The new application is to be designed and developed in such a manner that wherever possible any potential future change of finance system would have a reduced impact.