Iteration 1.3
Planned User Stories
Review & retrospective (learning points)
Attendees: - John Bannaghan (FIS Business Rep), Dawn Nicholls (Project Manager/Business Analyst), Peter Donoghue (Developer), Martin Jones (Developer), Mike McMonagle (Agile Mentor/Developer)
What went well?
- 2 more stories completed
- Refactoring undertaken to amd automated testing methods - this should help to improve velocity on future iterations as some complexity has been removed
What didn't go so well?
- Developer time conflicts with FIN087 and FIN08
- Developer annual leave
- 2 days Bamboo outage which meant that developers could only work locally
What will we do differently next iteration
- .