Iteration 1.2
Planned User Stories
Review & retrospective (learning points)
Attendees: - Douglas Stewart (Product Owner), John Bannaghan (FIS Business Rep), Dawn Nicholls (Project Manager/Business Analyst), Peter Donoghue (Developer)
Apologies: - Mike McMonagle (Agile Mentor/Developer), Martin Jones (Developer)
What went well?
- Most stories completed. FIN098-88 & FIN098-99 are only partially completed and will be carried forward into the next iteration.
What didn't go so well?
- Annual leave and resource conflicts from other projects has hindered progress for both Finance and IS Apps
- Didn't make good user of Jira to pass stories between the team
What will we do differently next iteration?
- Use Jira to pass stories between the team, in particular to pass across to Finance for testing