Iteration 1.10
Planned Stories
N.B. the technical storage of the attachments is still under debate so is preventing development of the key stories for this iteration. We have agreed that we will undertake the user interface design/development in parallel with ongoing discussions about the technical side. If agreement cannot be reached on the technical side by the end of week 1 of this iteration then alternative stories will need to be pull into this iteration and the attachment stories moved to a later iteration or dropped altogether.
Review & Retrospective
- 3 days developr time lost to leave, eAuth webservice issues, estimation meetings, file storage sulution investigating, and complexitites of Java file size validation
- SVN/Bamboo was out of action for 1 day
- This iteration contained a very large story (attachments) which had to be divided into smaller workable sections. Due to the complexity these were only delivered for UAT late in the iteration which meant that they were not tested in time. In future we should break these stories down before the iteration starts so that we can deliver functionality in smaller chunks